Go Back   Trackpads Community > General Discussions > Computer and Technology > Microsoft Applications

Microsoft Applications Discussions about Windows and other MS Products such as Office

Reply
 
LinkBack Thread Tools
Old 08-04-2005, 04:00   #1 (permalink)
Steve House [Project MVP]
Civilians

 
Default Re: how to going back to baseline in project?

The short answer is, you can't. A baseline is a snapshot of what the
schedule looked like when you created the baseline. While you can VIEW the
baseline to compare the present state of the project to it and thus see if
you are on track, there's no way to undo changes that have been made to the
project and roll it back to the state it was in when you saved the baseline.
If you don't have a backup - and you really should save a backup before
posting updates, just in case - you're out of luck.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Sergio" <Sergio@discussions.microsoft.com> wrote in message
news:00D06EC5-15AF-4615-A770-71589621ACD9@microsoft.com...
> from a project update to a previous state
>
> "Redneck David" wrote:
>
>> Back from what and where?
>>
>> "Sergio" wrote:
>>
>> > i need to going back to baseline dates. how i do that?


 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Trackpads Information
Click to Visit
Old 08-06-2005, 16:00   #2 (permalink)
Steve House [Project MVP]
Civilians

 
Default Re: how to going back to baseline in project?

Careful! Your "solution" has probably created more problems than it solved.
Remember, when you develop the plan, if you did it properly, you would NOT
have typed any dates into the Start and Finish columns - under normal
circumstances those are supposed to be calculated fields, NOT user-input.
Indeed, calcualting those dates is the whole reason for using Project in the
first place. The problem is that by copying back into the Start/Finish
columns there's a real good chance you have now set Start No Earlier Than or
Finish No Earlier Than constraints on those tasks, most of which are not
going to be justified and will completely screw up the plan's usability. If
you look at the indicator column down the left side of the Gantt chart entry
table you probably see a bunch of little calendar icons that weren't there
before (or shouldn't have been there before).
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Sergio" <Sergio@discussions.microsoft.com> wrote in message
news:8E04B644-6B1A-4D14-B899-0C76E2F9C275@microsoft.com...
> Hi Steve:
>
> Thanks for your answer. I found a solution, no very elegant, but a
> solution.
>
> First i made a backup (yes you are rigth), then turned all % to 0, then i
> opened the columns Baseline Start and finish, and copied each to Start and
> Finish columns. an that was all.
>
> Regards
>
> "Steve House [Project MVP]" wrote:
>
>> The short answer is, you can't. A baseline is a snapshot of what the
>> schedule looked like when you created the baseline. While you can VIEW
>> the
>> baseline to compare the present state of the project to it and thus see
>> if
>> you are on track, there's no way to undo changes that have been made to
>> the
>> project and roll it back to the state it was in when you saved the
>> baseline.
>> If you don't have a backup - and you really should save a backup before
>> posting updates, just in case - you're out of luck.
>> --
>> Steve House [MVP]
>> MS Project Trainer & Consultant
>> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>>
>>
>> "Sergio" <Sergio@discussions.microsoft.com> wrote in message
>> news:00D06EC5-15AF-4615-A770-71589621ACD9@microsoft.com...
>> > from a project update to a previous state
>> >
>> > "Redneck David" wrote:
>> >
>> >> Back from what and where?
>> >>
>> >> "Sergio" wrote:
>> >>
>> >> > i need to going back to baseline dates. how i do that?

>>
>>


 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply

Bookmarks

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Re: move entire project back to later date in Project Jan De Messemaeker Microsoft Applications 0 10-16-2005 14:05
project 2003 will not display baseline or progress =?Utf-8?B?Sm9obiBT?= Microsoft Applications 2 12-20-2004 10:00
baseline saved date in the project 2003 database =?Utf-8?B?VGFuemVlbQ==?= Microsoft Applications 1 12-12-2004 07:00
Linked Project Baseline? John Castle Microsoft Applications 1 06-16-2004 17:50
master project - baseline Itzik Microsoft Applications 1 06-16-2004 16:12


Community Information
Options
Quick Options
Trackpads Non-Commercial Ad
Copyright Information Click to Visit
Time
Server Time
All times are GMT -4. The time now is 13:52.
Copyright
Copyright Information
The header is based off of work by Vipixel.com and modified by this site. Trackpads and the Trackpads Logo are both Registered Trademarks of Jason Edwards and cannot be used without prior written permission.  The only exception is as a link back to this site. Trackpads is a private website run by a small legion of volunteers, 3 dogs, 12.5 cats and an army of small, super smart, bio-engineered mice with pointy hats and tutu's. Search Engine Friendly URLs by vBSEO 3.2.0 RC7
Archive Links
Archive Links
Page generated in 0.70331 seconds with 18 queries