Go Back   Trackpads Community > General Discussions > Computer and Technology > Microsoft Applications

Microsoft Applications Discussions about Windows and other MS Products such as Office

Reply
 
LinkBack Thread Tools
Old 06-16-2004, 18:34   #1 (permalink)
David Oliver
Civilians

 
Default Percent Complete vs. Percent Work Complete in Earned Value Calculations

It seems MSP uses % complete rather than % work complete
to compute earned value from planned value for a task or
project. This doesn't make sense to me given that
planned value is work X resource rate and %complete is
really a measure of duration rather than work. It's like
comparing apples and oranges. Using %complete instead of
%work complete also really skews the earned value on
partially completed tasks that have been split during
schedule statusing (Tools/Tracking/Update
Project/Reschedule uncompleted work to start after...)

So I am wondering if MSP provides a configuration option
that allows you to use %work complete to compute earned
value (BCWP), and consequently spi and cpi? Can anyone
help with that? Thanks in advance to anyone who replies
to this question!

 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Trackpads Information
Click to Visit
Old 06-16-2004, 18:34   #2 (permalink)
JulieS
Civilians

 
Default Re:Percent Complete vs. Percent Work Complete in Earned Value Calculations

David,

In Project 2002 and 2003 you can change the earned valued
calculation from % complete to physical % complete.
The physical % complete is a user entered value.
To switch to physical % complete:
Tools --> Options
Calculation tab
Click on the earned value button.

The other option would be to use custom fields with
formulas to calculate the earned value data based upon %
Work complete.

Hope this helps.
Julie
>-----Original Message-----
>It seems MSP uses % complete rather than % work complete
>to compute earned value from planned value for a task or
>project. This doesn't make sense to me given that
>planned value is work X resource rate and %complete is
>really a measure of duration rather than work. It's

like
>comparing apples and oranges. Using %complete instead

of
>%work complete also really skews the earned value on
>partially completed tasks that have been split during
>schedule statusing (Tools/Tracking/Update
>Project/Reschedule uncompleted work to start after...)
>
>So I am wondering if MSP provides a configuration option
>that allows you to use %work complete to compute earned
>value (BCWP), and consequently spi and cpi? Can anyone
>help with that? Thanks in advance to anyone who replies
>to this question!
>
>.
>

 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Old 06-16-2004, 18:40   #3 (permalink)
Steve House
Civilians

 
Default Re: Percent Complete vs. Percent Work Complete in Earned Value Calculations

Not quite so far fetched when you consider the default behavior of MSP is to
update work at the same rate at which it updates duration, unless you switch
it off in options. When you say that a 5 day duration task is 50% complete
you will be setting the work completed to what ever value should have been
done by the 50% duration mark. If it was a straightline 40 hour assignment,
50% duration will show up as also 50% work complete. If the task is
contoured, lets say 5 day duration with 1 hour on each of Mon, Tue, Wed,
Thur and 8 hours Fri for a total of 12 hours of work, 50% complete will show
we're at noon on Wed and as of this point we have done 2.5 hours of work for
21% work complete. Entering % Complete then indirectly computes the work
done as it was initially estimated and baselined and the BCWP reflects the
total work to have been performed after a duration equal to the % Complete.

Also, the SPI is a description of *schedule* performance not work. If the
SPI = 1, the duration we've actually worked up to the status date is equal
the duration represented by the status date. If it's <1, the duration
worked is what we would have done at some prior status date were we actually
on schedule. If we're behind schedule on 15 May, the BCWS will reflect the
work that would have been done were we 100% in line with our duration while
the BCWP relects the 100% duration level for a date equal to the status date
+ schedule variance. % Work Complete is actually more allied to the ACWP
than it is the BCWP as it reflects, among other things, how much work was
actually required for the tasks compared to how much we had estimated would
be required.

--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"David Oliver" <anonymous@discussions.microsoft.com> wrote in message
news:5b1701c42d58$05860e20$a001280a@phx.gbl...
> It seems MSP uses % complete rather than % work complete
> to compute earned value from planned value for a task or
> project. This doesn't make sense to me given that
> planned value is work X resource rate and %complete is
> really a measure of duration rather than work. It's like
> comparing apples and oranges. Using %complete instead of
> %work complete also really skews the earned value on
> partially completed tasks that have been split during
> schedule statusing (Tools/Tracking/Update
> Project/Reschedule uncompleted work to start after...)
>
> So I am wondering if MSP provides a configuration option
> that allows you to use %work complete to compute earned
> value (BCWP), and consequently spi and cpi? Can anyone
> help with that? Thanks in advance to anyone who replies
> to this question!
>



 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply

Bookmarks

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Progress Bar does not match percent complete =?Utf-8?B?R2xlbm4=?= Microsoft Applications 4 10-27-2004 16:00
%Work Complete vs. %Complete (Duration) in E.V. Calculations David Oliver Microsoft Applications 1 08-04-2004 02:47
Percent Work Complete Julie Microsoft Applications 2 06-16-2004 20:16
% Complete vs % Work Complete in Earned Value calculations David Oliver Microsoft Applications 1 06-16-2004 18:34
Actual work vs Percent Complete JD Microsoft Applications 2 06-16-2004 18:01


Community Information
Options
Quick Options
Trackpads Non-Commercial Ad
Copyright Information Click to Visit
Time
Server Time
All times are GMT -4. The time now is 18:06.
Copyright
Copyright Information
The header is based off of work by Vipixel.com and modified by this site. Trackpads and the Trackpads Logo are both Registered Trademarks of Jason Edwards and cannot be used without prior written permission.  The only exception is as a link back to this site. Trackpads is a private website run by a small legion of volunteers, 3 dogs, 12.5 cats and an army of small, super smart, bio-engineered mice with pointy hats and tutu's. Search Engine Friendly URLs by vBSEO 3.2.0 RC7
Archive Links
Archive Links
Page generated in 0.70466 seconds with 19 queries