![]() | ![]() | ![]() |
| |||||||
| Forums | Register | Groups | Awards | Arcade | Pets | T-Bucks / T-Store | Invite Your Friends | Blogs | Mark Forums Read |
| Microsoft Applications Discussions about Windows and other MS Products such as Office |
![]() |
| | LinkBack | Thread Tools |
| | #1 (permalink) |
| Civilians | Change your date display to include the time. The task probably does not start right at the very beginning of the day, so "one day's duration" (8 hours with the Standard calendar) would spill into the next day. Sarah |
|
| | #2 (permalink) |
| Civilians | Hi Luigui, First, set your date format to show you time as well as dates. (Tool ->Options, View tab, set the Date format to show time.) Project calculates information to the minute, so viewing time as well as the date can frequently help track down problems. On the Calendar tab in the Options dialog box, correct the default start and end times as well as modify the number of hours in a day and a week. It is this definition of "days" and "weeks" that Project uses when you enter task durations. So if your project calendar was modified for a 7.5 hour work day, but the definition of a "day" was 8 hours, the task will not end until 1/2 on an hour into the next working day. You may also want to check the start time of your Project (Project -> Project Information) to verify that the project is starting at the correct time. Hope this helps. Let us know how you get along. Julie "Luigui" wrote: > Whe using Mocrosift Project 2003. If I set a Task duration one day, the task > end day is next day instead of same day. How do I fix this setting problem? |
|
| | #3 (permalink) |
| Civilians | Hello Luigui, Have a look as the Mike Glen's site : http://pubs.logicalexpressions.com/P...Search&AUTH=23 #7 : Working Hours and Calendars. Gérard Ducouret "Luigui" <Luigui@discussions.microsoft.com> a écrit dans le message de news:05E6BBD7-6A56-4666-AF93-A593FF0D970E@microsoft.com... > Whe using Mocrosift Project 2003. If I set a Task duration one day, the task > end day is next day instead of same day. How do I fix this setting problem? |
|
| | #5 (permalink) |
| Civilians | Hi Luigui, Welcome to this Microsoft Project newsgroup :-) You might like to see FAQ Item: 5. Default Working Hours FAQs, companion products and other useful Project information can be seen at this web address: http://www.mvps.org/project/ Hope this helps - please let us know how you get on :-) Mike Glen Project MVP Luigui wrote: > Whe using Mocrosift Project 2003. If I set a Task duration one day, > the task end day is next day instead of same day. How do I fix this > setting problem? |
|
![]() |
| Bookmarks |
| Thread Tools | |
| |
Similar Threads | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Timescale Duration Bars = Actual Duration? | Holland | Microsoft Applications | 1 | 10-26-2005 14:16 |
| Re: How can I track a duration with an Actual Duration? | Jan De Messemaeker | Microsoft Applications | 1 | 07-29-2005 16:00 |
| Duration | =?Utf-8?B?WGFuZHJh?= | Microsoft Applications | 1 | 01-07-2005 11:00 |
| Elapsed duration & Fixed duration tasks | =?Utf-8?B?TWFyeSBBbm4=?= | Microsoft Applications | 7 | 12-28-2004 22:00 |
| Duration Box | Mike | Microsoft Applications | 5 | 07-14-2004 15:55 |
![]() | ![]() | ![]() |