Old 12-15-2004, 13:00   #1 (permalink)
Wilson, Jeff [CAR:3M30:EXCH]
Civilians

 
Default 2 questions from a Project newbee

I've input a ton of tasks/milestones and their dependencies in the Network
Diagram view and now want to do 2 key things ...

1) Select a task/milestone and show all transitive predecessors which affect
it (i.e. "Show me all the items which affect this item")
2) Select all the tasks/milestones owned by a resource and show all the
immediate predecessors for each of those tasks/milestones which are not
owned by that resource (i.e. "Show me all the people I need to talk to to
ensure my dependencies are satisfied")

How do I get Project to provide me this information? I know I can create
summary tasks, but we're at a point in the program where the
tasks/milestones are changing frequently, so I want to do all the processing
from the Network Diagram.

Thanks,
Jeff Wilson.


 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Trackpads Information
Click to Visit
Old 12-15-2004, 16:00   #2 (permalink)
John
Civilians

 
Default Re: 2 questions from a Project newbee

In article <cppka6$iqb$1@zcars0v6.ca.nortel.com>,
"Wilson, Jeff [CAR:3M30:EXCH]" <jtw@americasm01.nt.com> wrote:

> I've input a ton of tasks/milestones and their dependencies in the Network
> Diagram view and now want to do 2 key things ...
>
> 1) Select a task/milestone and show all transitive predecessors which affect
> it (i.e. "Show me all the items which affect this item")
> 2) Select all the tasks/milestones owned by a resource and show all the
> immediate predecessors for each of those tasks/milestones which are not
> owned by that resource (i.e. "Show me all the people I need to talk to to
> ensure my dependencies are satisfied")
>
> How do I get Project to provide me this information? I know I can create
> summary tasks, but we're at a point in the program where the
> tasks/milestones are changing frequently, so I want to do all the processing
> from the Network Diagram.
>
> Thanks,
> Jeff Wilson.


Jeff,
The first question is relatively easy but the second requires a little
more effort.

For the first part, set up a split screen (Window/Split). You can either
show the Network Diagram in the upper pane or the Gantt Chart. In my
opinion it is easier to select tasks from the Gantt Chart since the
Network Diagram takes up too much of the screen. In the lower pane show
the Relationship Diagram. For each task selected in the upper pane you
will see both predecessor and successor tasks so you will get a little
more than you requested.

Although there may be an alternate method for doing part two, I didn't
spend a lot of time researching it. For that kind of specialized format,
I generally go directly to a VBA approach. For the VBA approach here is
what I would do:
1. Set up a loop to tag all predecessor tasks that are performed by
resources other than the desired resource. In the loop, set a flag field
(e.g. Flag1) for all such predecessors
2. Set up a filter to show all tasks performed by the desired resource
AND all tasks with the flag field set. Do not display related summary
lines.
3. Apply the filter
You don't need a split view since the filter can be applied directly to
the Network Diagram. Just remember to clear the flag field for each new
resource. I recommend the flag be cleared before it is set in the code.

If you don't have experience with VBA, we can help with that.

Hope this helps.
John
Project MVP
 
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply

Bookmarks

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On

Similar Threads
Thread Thread Starter Forum Replies Last Post
Newbee help please Larry Web Design 0 10-26-2005 14:35
Project extension questions =?Utf-8?B?SmFjaw==?= Microsoft Applications 2 01-06-2005 12:00
Microsoft Office Specialist Certification for Microsoft Project questions Scott Brooks Microsoft Applications 1 01-02-2005 16:00
A few REALLY quick questions on Project Web =?Utf-8?B?QmVuIFNhdmFnZQ==?= Microsoft Applications 3 12-09-2004 04:00
2 questions - Project 2000 - Work scheduled is half of duration an =?Utf-8?B?TW9uaWNh?= Microsoft Applications 7 11-11-2004 22:55


Community Information
Options
Quick Options
Trackpads Non-Commercial Ad
Copyright Information Click to Visit
Time
Server Time
All times are GMT -4. The time now is 11:18.
Copyright
Copyright Information
The header is based off of work by Vipixel.com and modified by this site. Trackpads and the Trackpads Logo are both Registered Trademarks of Jason Edwards and cannot be used without prior written permission.  The only exception is as a link back to this site. Trackpads is a private website run by a small legion of volunteers, 3 dogs, 12.5 cats and an army of small, super smart, bio-engineered mice with pointy hats and tutu's. Search Engine Friendly URLs by vBSEO 3.2.0 RC7
Archive Links
Archive Links
Page generated in 0.60216 seconds with 19 queries