![]() | ![]() | ![]() |
| |||||||
| Forums | Register | Groups | Awards | Arcade | Pets | T-Bucks / T-Store | Invite Your Friends | Blogs | Mark Forums Read |
| Microsoft Applications Discussions about Windows and other MS Products such as Office |
![]() |
| | LinkBack | Thread Tools |
| | #1 (permalink) |
| Civilians | I run a woodwork manufacturing company and have been having trouble getting Project to do what I need. Is the following example possible? I need to cut 400 boards. I have a saw that can cut 10 boards and hour. I need project to tell me what the duration of this task will be given the resources I assign to it. Can I set up a total amount of work and a resource that has a fixed unit/hr rate with Project? I want to know when I need to throw extra resources at a project to finish ontime. If this is a double post, I appologize in advance. My previous posts weren't showing up. |
|
| | #2 (permalink) |
| Civilians | I would suggest creating a Fixed Unit task with Effort Driven flag set "on" for a Duration of 5 days. When you assign a Resource to that task at 100%, it will compute 40 hours of Work (400 boards divided by 10 boards per hour). Now, when you add another resource (assuming you have another saw to use), it will split the effort and give you two Resources at 20 hours of Work, recomputing the Duration to 2.5 days. Is that what you want to do? >-----Original Message----- >I run a woodwork manufacturing company and have been having trouble getting Project to do what I need. Is the following example possible? > >I need to cut 400 boards. I have a saw that can cut 10 boards and hour. I need project to tell me what the duration of this task will be given the resources I assign to it. Can I set up a total amount of work and a resource that has a fixed unit/hr rate with Project? > >I want to know when I need to throw extra resources at a project to finish ontime. > >If this is a double post, I appologize in advance. My previous posts weren't showing up. >. > |
|
| | #3 (permalink) |
| Civilians | Not exactly. I want to be able to tell Project that saw#1 can output 10 boards per hour, and I want Project to tell me that it will take 5 days at 8 hrs a day. Kind of backwards from what you described. Is this possible? I have a larger operation, this is just a small example to get me on the right track. "JohnG" wrote: > I would suggest creating a Fixed Unit task with Effort > Driven flag set "on" for a Duration of 5 days. When you > assign a Resource to that task at 100%, it will compute > 40 hours of Work (400 boards divided by 10 boards per > hour). Now, when you add another resource (assuming you > have another saw to use), it will split the effort and > give you two Resources at 20 hours of Work, recomputing > the Duration to 2.5 days. > > Is that what you want to do? > > >-----Original Message----- > >I run a woodwork manufacturing company and have been > having trouble getting Project to do what I need. Is the > following example possible? > > > >I need to cut 400 boards. I have a saw that can cut 10 > boards and hour. I need project to tell me what the > duration of this task will be given the resources I > assign to it. Can I set up a total amount of work and a > resource that has a fixed unit/hr rate with Project? > > > >I want to know when I need to throw extra resources at a > project to finish ontime. > > > >If this is a double post, I appologize in advance. My > previous posts weren't showing up. > >. > > > |
|
![]() |
| Bookmarks |
| Thread Tools | |
| |
Similar Threads | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Newbie | Bob St Clair | Microsoft Applications | 2 | 08-04-2005 12:00 |
| ***NEWBIE*** Godaddy subdomain/directories help ***NEWBIE*** | e-mail@nowhere.com | Web Design | 6 | 07-10-2005 00:00 |
| Newbie | =?Utf-8?B?S2FyZW4=?= | Microsoft Applications | 9 | 12-23-2004 19:00 |
| NEWBIE needs help | Robert McAnally | Microsoft Applications | 2 | 06-16-2004 04:01 |
| ~Newbie Needs Help | Charlie | Microsoft Applications | 4 | 06-16-2004 03:59 |
![]() | ![]() | ![]() |